NI, temperature analysis of molten metal,   smartdip, cast iron, furnace, thermal analysis, gas furnace..





smartpour

smartdip
peakdip
DPP
nical

Digicarb 3
digicarb 2d

 

Smartpour on autopours 2
back to part 1

Installation in USA
The client supplied nodular iron castings for the automotive industry. The installation foundry had four Disamatic moulding lines, two with DUCA presspour ladles, each fitted with laserpour metal level control. The infrared temperature measurement system supplied was similar to the Potterton system. Range: 2000 to 4000oF. Threshold: 2350oF. Target distance: 12ft. (3.7m). The head with its air purge was suspended from an inverted swivel base, which was bolted to an extension plate, welded to the main body of the Duca ladle. The molten stream was viewed from the moulding machine, looking down the line, with a background of flame & fume. The main electronics unit was installed in the basement, below the level of the moulding line. The operator's module was installed on the operator's platform, which was at a level above the head assembly. The system was installed and commissioned during the last week of October 1997. The client's routine procedure was to take a dip temperature in the bowl before the stopper every 15 minutes. These readings are manually logged and the dip temperature reading was held on a wall mounted indicator, until updated by the next measurement.

  Problems dealth with
1. During the commissioning period the head was installed in three different positions, to minimise extraneous readings, caused by metal dribble, when the stopper rod was closed. Readings were flashed up on the displays, but without arriving at a 'good measurement' decision by the program.
2. Longer than usual securing bolts and spring washers were fitted to the head assembly as an anti-vibration precaution.
3. The computer downloading facility was checked during the commissioning period but could not be finalised due to cable routing decisions.
4. The cycling characteristic was recognised and accepted as normal by Intermet. The two position automatic auxiliary heating control system on the Duca autopour plus the regular addition of metal from any one of three holding furnaces are involved variables.
Developments

1. At the American client's request, since the commissioning, the measurement program had been modified to simplify the operator's temperature display, giving only final decision temperatures and holding this reading for up to ten seconds after measurement, or until superseded by a new reading. This modification has also been incorporated in the Potterton program.
2. The Windows computer input program has been adopted as standard for data downloading.

Observations
1. At Matsushita the target +/- 10oC tolerance was achieved by the end of the commissioning period.
2. The interference problem from the nodularisation process could be overcome by avoidance ie. changing the target stream.
3. The location of the head at Matsushita ie. looking back towards the moulding machine eliminated any flame interference from the previous casts down the line. However, this advantage is offset by the need to water cool the head.
4. The latest two installations detailed have both modified procedures at the autopour since installing infrared systems. One foundry had significantly reduced the number of dips taken in the bowl before the pouring nozzle. The other foundry had changed some of its target pouring temperatures.
5. Duca Inc, North American autopour manufacturers, have taken a positive interest in the infrared installation at the American client's foundry. Where auxiliary heating was fitted, it supplied a two position control system. It has two levels of heating; high and low power. Pre-set timers were fitted, controlling the heating period at high and low level. These timers were adjustable, allowing the heating control to be varied, by the autopour user.
6. Fitting the infrared detector head to the mainframe of the autopour enabled the head to measure along a fixed line of sight. However, there were disadvantages:
 Optical - The ratio thermometer did not require its target retical to be completely filled or overlapped by the target. The rule of thumb, for infrared detectors, is to site the head as far back from the target as practicable. Five metres would be the optimum distance for the detector used on most autopours. Metal dribble can cause extraneous readings which show on the main electronics unit. These have been masked out on the operator's display, since they never constitute a good stable acceptable reading.
 Mechanical - Anti-vibration precautions were necessary for the head assembly. Protection from impact by manually operated equipment and metal splash was essential.
 Ambient temperature - 55oC (130oF) is the maximum operating temperature for the infrared head. Heat was transmitted by conduction through the metal framework of the ladle in addition to radiation from the body of the ladle in addition to that from molten metal. This could be overcome by use of a water cooled jacket and cable protection.
7. Quality control was the main thrust of interest in an automatic pouring temperature monitor. This requirement had been satisfied both in the QC department and at the ladle operator's station. The system is now established as 'user friendly'.
8. An additional positive interest was automatic temperature control of ladle pouring temperature which emerged, at one of the detailed installations.
9. As an example the installation of equipment in the USA was carried out in one day by a team of three, two NI(L) plus one of their staff, with assistance from the maintenance department. Commissioning was completed in a further 2 1/2 days and included a well attended information meeting.
10. Within a few weeks of handover, after a plant breakdown on line A, the temperature monitoring system was transferred to line C, the other autopour unit. This transfer, alignment and calibration was carried out by Intermet staff, without reference to Northern Instruments or TNI Industrial, the USA representative.
11. A member of Intermet's staff commented, that the equipment was 'only as smart as you make it'. It must be aligned correctly and calibrated against a reliable standard.
Calibration
The normally recommended calibration procedure for infrared thermometers was to remove from plant and calibrate, in the laboratory, on a black body furnace. A two colour or ratio thermometer was different in that it had an emissivity slope control potentiometer, active in the 'gray body' switch position, applicable for molten metal. In the laboratory, the emissivity slope potentiometer is set at 1.00 for calibration on a black body furnace, which does not reproduce conditions on plant. Back on plant, after recalibration, use a dip pyrometer, with a current calibration certificate plus new thermocouple to measure the autopour bowl temperature and adjust the e-slope setting on the infrared head, to match the dip temperature. Alternatively, a Disappearing Filament Pyrometer (DFP) with a current calibration certificate may be used to measure the metal stream temperature.

 

Conclusions
1. All three of the installations described have obtained consistent results which fit in with their existing method of temperature measurement, either immersion thermocouple or optical pyrometer, within acceptable tolerance limits.
2. A significant increase in the amount of temperature information has been established at the autopour.
3. Temperature trends may be developed from the regular and frequent data now available.
4. This information is also available for storage, printing and further processing via a non-dedicated computer, using the Windows Input program provided.
5. Automatic pouring temperature control of the autopour appears to be a realistic target, perhaps utilising a Brilliantpour, which will require the addition of safety interlocks plus close liaison with the user and ladle manufacturer.
6. Close liaison and support at all three foundries were important factors in achieving successful installations.

Bibliography
Performance report on Smartpour. Case studies. F G Bargh & G R Barnes, 1996 AFS Transactions, ref. 96-09.
Acknowledgements

The author wishes to acknowledge the assistance and co-operation received from Matsushita Refrigeration Industries (S) Pte Ltd, Singapore; Potterton Myson Ltd, UK; and the client in the USA.

 



contacts
Copyright © Northern Instruments - 2000.